Zilber Property Group
Construction Project PortalIndustrial Development
Caledonia Corporate Park · I-94 Corridor · Southeast Wisconsin

Zilber Industrial 4 — Caledonia UNDER CONSTRUCTION SPECULATIVE

251,872 SF Class A Industrial Shell Architect: ZA Studios GC: Scherrer Construction
Zilber Industrial 4 — site plan SITE PLAN · brochure ↗
Zilber Industrial 4 — building rendering BUILDING RENDERING · brochure ↗

Schedule · 9% · to Occupancy Feb '27

Current: Site grading & utilities · building permit in review
Next: Foundations & precast — grade beams begin Jul 20
For-Construction docs
Jun 9 · arch + civil released (ZA Studios)
Trades contracted
Jun 25 · Scherrer executed; majors bought out
Permitting
In review · Village utility comments open, permit pending
Sitework
Active · mobilized; mass grading mid-July
Foundations & precast
Next · grade beams Jul 20 → precast early Oct

Building Specs

Available Space251,872 SF (Divisible)
Building Size251,872 SF
Office SpaceTo Suit
Clear Height32'-0"
Car Parking176 Spaces
Trailer Parking15 (On-Building)
Loading26 Docks (Exp.) · 2 Drive-In
Bay Size51' × 54' · 60' Speed Bay
Fire ProtectionESFR System
Power3,000 Amps (Expandable)
LightingHigh Bay LED
ConstructionPre-Cast Panel

Milestone Timeline

Land & Due Diligence
Closed
Done
Site acquired in Caledonia Corporate Park — a 90-acre master-planned industrial park on the I-94 corridor in Racine County. Due diligence and closing complete.
Design & Construction Docs
For-Construction set issued Jun 9, 2026
Done
ZA Studios (Zimmerman Architectural) issued the For-Construction set 6/9/26 — architectural and civil (Pinnacle Engineering on civil). CAD floor plans released to the team.
Arch setCivil plans
Preconstruction & Permitting
Through Sep 14, 2026
Active
FP / plumbing / HVAC / electrical design & permitting underway. Building permit applications submitted 6/19. Village of Caledonia water & sanitary utility plan-review comments being addressed (Pinnacle). Geotech / soil testing complete (Reesman's, 6/16).
Schedule
Trade Buyout
Remaining contracts in progress
In progress
Scherrer design-build contract executed 6/25. Major trade packages awarded — Reesman's (earthwork & site utilities), ATMI (precast), Cardinal (structural steel), Middleton (concrete), All American (roofing). A few small-ball categories remain to award and contract.
Procurement — Shops & Submittals
Through Oct 28, 2026
Active
Precast wall-panel shop drawings (ATMI, fab into early Oct), structural steel shops (Cardinal, into mid-Oct), concrete rebar, fire pump, fire-alarm permit, light-fixture lead, and electrical switchgear (using Zilber stock).
Sitework
Active · runs through Apr 2027
Active
Mobilization & erosion control complete (6/19). Strip topsoil → mass grading mid-July → site plumbing (water / sanitary / storm) late July. Site-protection plan under discussion with Reesman's — curb tile, pad drain tile, extra stone/binder, Portland stabilization (see Open Items).
Utility plan
Structure & Enclosure
Jul 20, 2026 – Jan 6, 2027
Upcoming
Grade beams & interior column pads → set precast wall panels (early Oct) → set roof steel (late Oct) → roofing (early Dec) → storefront entrances & overhead doors.
Interior Rough & Finish
Aug 13, 2026 – Feb 22, 2027
Upcoming
Underslab sanitary → roof storm piping → sprinkler system → warehouse slab on grade (mid-Jan ’27) → floor sealer → MEP rough & finish → final inspections.
Substantial Completion
Target late Feb 2027
Upcoming
Final inspections ~Feb 9, punchlist Feb 16–22, 2027.
Final Paving & Closeout
Surface asphalt Apr 2027
Upcoming
Surface asphalt course placed late April 2027 (weather-dependent paving window).
Per Scherrer P6 schedule · rev 06.25.26

Open Items & Decisions

Site-protection plan decision High
Decision · Reesman's / Scherrer / ZPG · target Jul 02
Reesman's submitted site-protection options & exhibits 6/26 to protect the parking-lot subsoils and building pad through construction until full restoration.
Options on the table
• 6″ tile between curb and building
• Two building-pad drain-tile options (Pad Tile 8 / Pad Tile 10)
• Inlet adjustments if cb/inlets are left low this year, raised 2027
• Extra stone vs. asphalt binder, per construction traffic
• Portland stabilization of the pad
Allowances — Reesman's: pad maintenance, construction entrance · ZPG: dewatering, undercuts, winter conditions, site protection
Site stewardship — grade to drain, utility trenches as French drains, essential traffic only on the pad, rut repairs, traffic management
Next: select the option set at the Thursday 7/2 meeting with Scherrer & Reesman's; sequence against the P6 schedule.
Exhibits: Curb Tile, Pad Tile 8/10, Extra Stone Areas, Site Options spreadsheet.
Issue remaining trade contracts High
Buyout · Zilber / Scherrer · due Jul 03
Major packages are bought out; the remaining small-ball trade categories still need to be awarded and contracted through Scherrer. Targeting completion the week of June 30.
Village utility plan review High
Approval · Pinnacle / ZPG · due Jun 27
Respond to the Village of Caledonia water & sanitary plan-review comments (revised civil by Pinnacle). Required before the building permit can be released.
Utility plan
Building permit issuance High
Permit · Village of Caledonia · due Jul 02
Building permit applications submitted 6/19; issuance pending utility sign-off and the Village's final review.
Precast shop drawings Med
Submittal · ATMI / ZA Studios · due Jul 08
ATMI precast wall-panel shop drawings are out for review/approval. Long-lead item that drives the early-October precast set date.
Structural steel submittal Med
Submittal · Cardinal · due Jul 10
Cardinal structural-steel shop drawings — long-lead; expedite to hold the late-October steel erection window.
Tap any item for detail · status as of latest update

Closed Items

No items closed yet. When an issue is resolved, its conclusion is stated here and the item moves from Open Items to Closed.

Project Drawings — Self-Serve

For-Construction set, individual key sheets, and CAD files.
Key Sheets
PDF
Site Plan · C-4 · 4.3 MB
PDF
First Floor Plan · A2.1 · 1.3 MB
PDF
Site Utilities · C-10 · 3.6 MB
PDF
Exterior Elevations · A4.0 · 2.7 MB
Full Set & CAD
PDF
Architectural / Structural · Rev 06.09.26 · 7 MB
PDF
Civil — Plans · C-1–C-14 · 8.6 MB
PDF
Civil — Details · C-15–C-17 · 2.4 MB
PDF
Civil — Landscape · L-1–L-4 · 3.9 MB
DWG
Floor Plan — Overall · A2-1 · CAD
DWG
Floor Plan — Part A · A2-1a · CAD
DWG
Floor Plan — Part B · A2-1b · CAD
Direct file links · drawings courtesy ZA Studios
🔒